Greater Anglia is due to carry out maintenance work on weekends throughout February.
Here is how you may be impacted if you are planning on travelling during the engineering works.
Saturday February 2
London Liverpool Street to Colchester, Ipswich, Norwich and branches
A revised timetable will be in operation because of planned engineering work which is taking place between London and Romford.
As a consequence, trains from Norwich/Ipswich/Clacton/Colchester will terminate at Shenfield.
Passengers are to alight at Ingatestone where connecting Rail Replacement Buses will operate forward to Newbury Park.
At Newbury Park, TfL Central Line underground services will convey passengers to Stratford and London Liverpool Street.
Due to Overhead Line Renewals Work, buses will also replace trains between Shenfield and Southend Victoria/Southminster on this day.
Tickets will be accepted on the TfL Central Line between Newbury Park and Stratford / Liverpool Street
Sunday, February 3
London Liverpool Street to Colchester, Ipswich, Norwich and branches
A revised timetable will be in operation because of engineering work which is planned to take place between London and Witham.
As a consequence, trains from Norwich/Ipswich/Clacton/Colchester will terminate at Witham.
At Witham connecting Rail Replacement Buses will operate forward to Newbury Park. At Newbury Park, TfL Central Line underground services will convey passengers to Stratford and London Liverpool Street.
Due to Overhead Line Renewals Work, buses will also replace trains between Shenfield and Southend Victoria/Southminster on this day.
Tickets will be accepted on the TfL Central Line between Newbury Park and Stratford / Liverpool Street
Saturday, February 9
London Liverpool Street to Colchester, Ipswich, Norwich and branches
A revised timetable will be in operation because of planned engineering work which is taking place between London and Romford.
As a consequence, trains from Norwich/Ipswich/Clacton/Colchester will terminate at Shenfield.
Passengers are to alight at Ingatestone where connecting Rail Replacement Buses will operate forward to Newbury Park.
At Newbury Park, TfL Central Line underground services will convey passengers to Stratford and London Liverpool Street.
Due to Overhead Line Renewals Work, buses will also replace trains between Shenfield and Southend Victoria/Southminster on this day.
Tickets will be accepted on the TfL Central Line between Newbury Park and Stratford / Liverpool Street
Sunday, February 10
London Liverpool Street to Colchester, Ipswich, Norwich and branches
A revised timetable will be in operation because of engineering work which is planned to take place between London and Witham.
As a consequence, trains from Norwich/Ipswich/Clacton/Colchester will terminate at Witham.
At Witham connecting Rail Replacement Buses will operate forward to Newbury Park. At Newbury Park, TfL Central Line underground services will convey passengers to Stratford and London Liverpool Street.
Due to Overhead Line Renewals Work, buses will also replace trains between Shenfield and Southend Victoria/Southminster on this day.
Tickets will be accepted on the TfL Central Line between Newbury Park and Stratford / Liverpool Street
Saturday, February 16
London Liverpool Street to Colchester, Ipswich, Norwich and branches
As a result of Bridge Repair Works at Manningtree, buses will replace trains between Colchester/Manningtree and Ipswich from 11.30am on Saturday.
The Harwich branch service will operate to revised timings.
On this day buses also replace trains between Shenfield and Southend Victoria/Southminster, as a result of Overhead Line Renewals Work.
Sunday, February 17
London Liverpool Street to Colchester, Ipswich, Norwich and branches
As a result of Bridge Repair Works at Manningtree, buses will replace trains between Colchester/Manningtree and Ipswich on Sunday.
The Harwich branch service will operate to revised timings.
On this day buses also replace trains between Shenfield and Southend Victoria/Southminster, as a result of Overhead Line Renewals Work.
Tickets will be accepted on the TfL Central Line between Newbury Park and Stratford / Liverpool Street
Saturday, February 23
London Liverpool Street to Colchester, Ipswich, Norwich and branches
A revised timetable will be in operation because of engineering work which is planned to take place between London and Witham.
As a consequence, trains from Norwich/Ipswich/Clacton/Colchester will terminate at Witham.
At Witham connecting Rail Replacement Buses will operate forward to Newbury Park.
At Newbury Park, TfL Central Line underground services will convey passengers to Stratford and London Liverpool Street.
Due to Overhead Line Renewals Work, buses will also replace trains between Shenfield and Southend Victoria/Southminster on this day.
Tickets will be accepted on the TfL Central Line between Newbury Park and Stratford / Liverpool Street
Sunday, February 24
London Liverpool Street to Colchester, Ipswich, Norwich and branches
A revised timetable will be in operation because of engineering work which is planned to take place between London and Witham.
As a consequence, trains from Norwich/Ipswich/Clacton/Colchester will terminate at Witham.
At Witham connecting Rail Replacement Buses will operate forward to Newbury Park. At Newbury Park, TfL Central Line underground services will convey passengers to Stratford and London Liverpool Street.
Due to Overhead Line Renewals Work, buses will also replace trains between Shenfield and Southend Victoria/Southminster on this day.
Tickets will be accepted on the TfL Central Line between Newbury Park and Stratford / Liverpool Street
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel